Primary substation and feeder reinforcement
Substation design and network reinforcement for an industrial area approaching its firm capacity limit.
- Sector
- Power distribution
- Location
- Regional
- Year
- 2024
- Scope
- Studies, design and tender support
The engagement
01
The problem
Load growth had eroded the reserve on an ageing distribution network. Any single incomer outage would have taken production offline across several industrial tenants.
02
Our approach
A full load-flow and fault study established the true constraint, which proved to be protection discrimination rather than raw capacity. The design combined a new primary substation with reconfigured feeders and a corrected coordination scheme.
03
The outcome
Firm capacity restored with documented selectivity across the network, and maintenance now possible without an operational shutdown.